one to one relationships between QC and TFS projects

Last post 03-02-2010 12:27 by ilpo. 1 replies.
Page 1 of 1 (2 items)
Sort Posts: Previous Next
  • 03-02-2010 12:19

    • Kundan K
    • Top 50 Contributor
    • Joined on 09-08-2009
    • Points 240

    one to one relationships between QC and TFS projects

    As per current setup in QC there is Just one project as “PRISM” and that is mapped with separate projects in TFS (i.e. Enquiries, Euroclear CCI ..). So that is one to many relationships. However now we want to change the existing setup in QC and want to have separate project in QC as well. So now one to one relationships would be required between QC and TFS. Is possible to have? Please suggest. Thanks.

    • Post Points: 20
  • 03-02-2010 12:27 In reply to

    • ilpo
    • Top 10 Contributor
      Male
    • Joined on 06-16-2006
    • Espoo, Finland
    • Points 50,730
    • Juvander Consulting

    Re: one to one relationships between QC and TFS projects

    One to One is actually simpler than one to many.

    So take ErrorDB -field out from settings and leave Destination Project on both TFS and QC project settings. Destination Project is then the one where all new items will be created.

    //Ilpo